Assistance at provisional and final acceptance
What is not recorded at handover is hard to enforce afterwards. We make sure it is recorded.
According to case law and practice, visible defects that are not listed in the official record (proces-verbaal) at provisional acceptance are deemed accepted; what that means in your case depends on your contract. A technical expert at your side sees what you do not see, measures what may be disputed and has it entered in the record.
Who it is for
Buyers of a new-build house or flat, especially those buying from a developer under the Breyne Act (Wet Breyne): the architect is usually appointed by the developer, so you have no technical adviser of your own at the table.
Clients commissioning a renovation or new build who want to know, at the end of the works, whether what is handed over matches what was ordered and paid for.
Associations of co-owners and property managers (syndici) who must accept the common parts of a block of flats or a business park and want a technical expert to substantiate their reservations.
How it works
- File review in advance. We read the contract, the specifications, the drawings and the energy performance (EPB) and safety documents, and draw up a checklist per room and per element, with the applicable standards and tolerances.
- Our own preliminary walk-round. Where possible we inspect the building before the official handover, so that on the day itself we know where to look. For common parts we compare what has been built with the planning permission and the deed of division (basisakte).
- Walk-round at the handover. Together with you, the contractor or developer, and the architect. We measure what can be measured: flatness and level differences, falls, parking bay depth, embankment slope, ventilation, operation of installations. Each defect gets a photo, a location and, where possible, a reference to a standard.
- Report and official record. You receive a list of defects per room that can go straight into the record of provisional acceptance, with the reservations that are technically sound. We do not sign the record on your behalf; we make sure you know what you are signing.
- Follow-up until final acceptance. At your request, we check whether the recorded defects have actually and correctly been remedied, and whether new ones have appeared during the guarantee period, before you sign off definitively.
Before you buy or sign
Anyone who buys or takes delivery of a house, flat or commercial building usually signs for everything at one moment: the condition of the building, the defects still to be remedied and the conditions under which that will happen. What has not been established and recorded at that moment is hard to enforce afterwards. That is why we combine two things before you sign.
The technical inspection. We go through the building or flat with you, using measurable criteria and the applicable standards and technical information notes as the yardstick. You receive a list of defects per room and per element, with photos, measurements and references to standards, in a report you can use directly in the handover record or in negotiations with the seller.
The legal review. For the contractual side we work with a law firm specialising in construction law, or with your own lawyer. They review the sale agreement, the construction contract or the official record: which reservations to have included, which time limits are running and what you do and do not accept by signing.
The result: you sign with full knowledge of the facts, with a technical report and a legally reviewed document in hand. If you only want the technical inspection, that is of course possible too.
What you can expect from us
Attention to detail. A handover is won or lost on the details: the scratch nobody noticed, the fall that is just off, the missing fire damper. We work with a checklist per room and per element and leave nothing to chance.
Knowledge of the standards and of good workmanship. A defect you can only call 'ugly' is waved away by a contractor. A defect that exceeds a tolerance from a technical information note is not. We name every point with its yardstick, and we deliberately strike out the standards that do not apply, so your list stays credible.
Reporting that stands up. Our report is written to be used: in the official record, in a formal notice of default, and if need be in an expert investigation. We bring the same thoroughness as a technical adviser in a dispute; the handover is where it starts.
Costs
Hourly rate for file review, walk-round and report, plus travel costs, excluding VAT. We estimate the hours in advance based on the scope: a house or flat, or the common parts of a building or business park. A follow-up visit before final acceptance is estimated separately.
Standards and legislation
- Breyne Act (Act of 9 July 1971): protection for anyone buying a house or flat that is yet to be built or under construction, with the mandatory two-stage acceptance: final acceptance follows no earlier than one year after provisional acceptance (Art. 9), and only after the common parts, including the accesses, have been finally accepted; in practice this is called the 'guarantee period'. Under certain conditions the Act also applies to the sale of a house that the seller is still renovating or extending (Art. 1, second paragraph).
- Ten-year liability of contractor and architect (Civil Code): according to case law and legal doctrine, it begins at acceptance of the works; with a two-stage acceptance that is in principle the final acceptance, unless the contract designates the provisional one. Under the Breyne Act it also applies to the seller (Art. 6). So read your contract, and make sure the official record is correctly dated and complete.
- Buildwise technical information notes (TV): the tolerances against which finishes are assessed, such as TV 237 and TV 276 for indoor and outdoor tiling, TV 272 for parquet, TV 258 for ventilation, TV 244 and TV 280 for flat roofs.
- Standard Specification 250 (Standaardbestek 250), VLARIO guidelines and Eurocode 7 for external paving, sewerage, swales and earthworks in common parts and business parks.
- AREI (Belgian electrical installations regulations) and the inspection reports for electrical installations; fire certificates and hydrants according to fire service regulations.
Only just on the drawing is not the same as fitting in reality. That is why we measure on site, not on the drawing.
ir. Ben Verlinden
Questions about handover inspection
What is the difference between provisional and final acceptance?
Provisional acceptance establishes that the works are complete and records the defects still to be remedied in an official record (proces-verbaal); from then on you take the building into use. Final acceptance follows after a guarantee period, under the Breyne Act at least one year later, and confirms that the defects in the record have been remedied and that no new ones have appeared.
Which defects should you have recorded at provisional acceptance?
Everything that is visible, however small: scratches in glazing and joinery, damaged tiles, walls that are not flat, missing finishes, doors that do not close properly, dripping taps. In addition, everything that can be measured: flatness of floors, falls on terraces, ventilation flow rates, operation of installations. A visible defect that is not in the record is, as a rule, deemed accepted.
What if you sign the record without reservations?
Then the visible defects are, as a rule, deemed accepted, especially if your contract designates provisional acceptance as acceptance of the works; afterwards they are hard to invoke. The ten-year liability (Articles 1792 and 2270 of the former Civil Code) and, according to case law, liability for minor latent defects do continue to apply. Under the usual contracts, whatever you record as a reservation should be remedied before final acceptance.
Do you also assist associations of co-owners with the common parts?
Yes. Acceptance of the common parts of a block of flats or a business park is technically the most demanding: roofs, façades, sewerage, external paving, swales (wadi's), fire safety, plant rooms. We carry out our own preliminary walk-round, walk the site with the board of co-owners and the property manager (syndicus), and deliver a report that the association of co-owners uses as the basis for its reservations.
What does assistance at a handover cost?
We charge by the hour, plus travel costs, and estimate the number of hours for the walk-round and the report in advance. For a house or flat, half a day on site plus the report is usually enough; common parts take more. Weigh that against a single unrecorded defect you later have to remedy yourself.
Related
Discuss your case
A first conversation is free of obligation. Book a time straight away, or send us your question through the form.